• xmlui.mirage2.page-structure.header.title
    • français
    • English
  • Help
  • Login
  • Language 
    • Français
    • English
View Item 
  •   BIRD Home
  • LAMSADE (UMR CNRS 7243)
  • LAMSADE : Thèses
  • View Item
  •   BIRD Home
  • LAMSADE (UMR CNRS 7243)
  • LAMSADE : Thèses
  • View Item
JavaScript is disabled for your browser. Some features of this site may not work without it.

Browse

BIRDResearch centres & CollectionsBy Issue DateAuthorsTitlesTypeThis CollectionBy Issue DateAuthorsTitlesType

My Account

LoginRegister

Statistics

Most Popular ItemsStatistics by CountryMost Popular Authors
Thumbnail

Accélération des projets de fabrication et modélisation de l’impact de la main d’œuvre additionnelle sur la qualité

Project crashing with overtime and temporary work under quality constraints

Bou Orm, Mayassa (2017), Accélération des projets de fabrication et modélisation de l’impact de la main d’œuvre additionnelle sur la qualité, doctoral thesis prepared under the supervision of Jeunet, Jully, Université Paris dauphine

View/Open
2017PSLED084.pdf (13.07Mb)
Type
Thèse
Date
2017-07-04
Metadata
Show full item record
Author(s)
Bou Orm, Mayassa
Under the direction of
Jeunet, Jully
Abstract (FR)
Cette thèse s'inscrit dans la littérature relative au problème d'arbitrage durée, coût et qualité en gestion de projet. Nous développons un modèle d'accélération des projets de fabrication par le recours au travail temporaire et aux heures supplémentaires. Nous prenons en compte l'impact de la main d'œuvre additionnelle sur la durée via les pertes de productivité et sur la qualité des activités qui composent le projet. La qualité de toute activité est mesurée par le pourcentage d'items validés dans sa check-list de contrôle qualité. Nous proposons une formulation linéaire du problème de minimisation de la durée du projet sous contrainte de budget et de respect d'un seuil de qualité minimum pour chacune des activités que le projet comporte. Le programme d'optimisation mixte qui en résulte est appliqué au cas d'un projet de fabrication d'une motrice TGV et permet d'obtenir une planification prévisionnelle de la main d'œuvre pour atteindre la durée optimale d'exécution. Le modèle peut également être utilisé pour accélérer un projet en cours d'exécution ou à des fins plus stratégiques de dimensionnement des postes de travail.
Abstract (EN)
We address the discrete time resource-constrained project scheduling problem in which each activity has a specified work content and its resource usage may vary from period to period. We consider temporary work and overtime as additional renewable resources for crashing the project. We assume that the project quality may be affected by crashing as well as its completion time through productivity loss due to overmanning. We develop a Mixed-Integer Linear Programming (MILP) model to minimise the makespan subject to a budget constraint and to acceptable quality levels for all activities so as to avoid rework. The proposed approach is applied to an actual manufacturing project of a very high speed train motor coach.
Subjects / Keywords
Gestion de projet; Accélération; Arbitrage durée - coût et qualité; Travail temporaire; Heures supplémentaires; Productivité; Programmation linéaire; Project management; Time Resource Quality Trade-Off; Flexible resource profiles; Overmanning; Overtime; Productivity loss; Linear programming; Case study

Related items

Showing items related by title and author.

  • Thumbnail
    Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem 
    Jeunet, Jully; Bou Orm, Mayassa (2018) Article accepté pour publication ou publié
  • Thumbnail
    Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem 
    Jeunet, Jully; Bou Orm, Mayassa (2020) Article accepté pour publication ou publié
  • Thumbnail
    Time Cost Quality Trade-off Problems: A survey exploring the assessment of quality 
    Bou Orm, Mayassa; Jeunet, Jully (2018) Article accepté pour publication ou publié
  • Thumbnail
    Formation en entreprise et débauchage de main d'oeuvre aux Etats-Unis : un modèle dynamique d'action collective 
    Caroli, Eve; Huberman, Bernardo; Glance, Natalie (1995) Article accepté pour publication ou publié
  • Thumbnail
    Le rôle de la spatialité dans la mise en place du New Model Worker : du projet Valmy aux tours de la Défense de la Société Générale 
    Minchella, Delphine (2015-05) Thèse
Dauphine PSL Bibliothèque logo
Place du Maréchal de Lattre de Tassigny 75775 Paris Cedex 16
Phone: 01 44 05 40 94
Contact
Dauphine PSL logoEQUIS logoCreative Commons logo